Contract No: HK/2015/01

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 3)

 

Environmental Permit no. EP-364/2009/E,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/E,  FEP-12/364/2009/D

 

Monthly Environmental Monitoring & Audit Report

 

- MAy 2018 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and                                            

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

 

June 2018


Table of contents   

 

EXECUTIVE SUMMARY.. 4

1     Introduction.. 10

1.1         Scope of the Report 10

1.2         Structure of the Report 10

2     Project Background.. 12

2.1         Background. 12

2.2         Scope of the Project and Site Description.. 12

2.3         Division of the Project Responsibility. 13

2.4         Project Organization and Contact Personnel 14

3     status of regulatory compliance.. 21

3.1         Status of Environmental Licensing and Permitting under the Project 21

4     Monitoring Requirements. 34

4.1         Noise Monitoring. 34

4.2         Air Quality Monitoring. 36

5     Monitoring Results. 38

5.1         Noise Monitoring Results. 39

5.2         Real Time Noise Monitoring Results. 41

5.3         Air Quality Monitoring Results. 44

5.4       Waste Monitoring Results. 49

6     Compliance Audit.. 55

6.1         Noise Monitoring. 55

6.2         Air Quality Monitoring. 57

6.3         Review of the Reasons for and the Implications of Non-compliance. 58

6.4         Summary of action taken in the event of and follow-up on non-compliance. 59

7     Cumulative Construction Impact due to the Concurrent Projects  59

8      Enviromental site audit.. 61

9      Complaints, Notification of Summons and Prosecution.. 63

10    Conclusion.. 64


lIST OF TABLES

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental  

                      protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no.     

                      HK/2009/01

Table 3.3      Summary of submission status under FEP-02/364/2009

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no.  

                      HK/2009/02

Table 3.5      Summary of submission status under FEP-01/364/2009

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no.  

                      HY/2009/18

Table 3.7      Summary of submission status under FEP-05/364/2009/A

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no.  

                     HY/2009/15

Table 3.9      Summary of submission status under FEP-06/364/2009/A

Table 3.10    Cumulative Summary of Valid License and Permits under Contract no. HY/2009/19

Table 3.11   Summary of submission status under FEP-07/364/2009/D

Table 3.12    Cumulative Summary of Valid License and Permits under Contract no. HK/2012/08

Table 3.13    Summary of submission status under FEP-12/364/2009/D

Table 3.14    Cumulative Summary of Valid License and Permits under Contract no. HY/2010/08

Table 3.15    Summary of submission status under FEP-10/364/2009/B

Table 3.16    Cumulative Summary of Valid License and Permits under Contract no. HY/2011/08

Table 3.17    Summary of submission status under FEP-11/364/2009/E

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Quality Monitoring Stations

Table 5.1      Noise Monitoring Stations for Contract no. HY/2009/18 (NOT USED)

Table 5.2      Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.3      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.5      Noise Monitoring Stations for Contract no. HY/2010/08

Table 5.6      Noise Monitoring Stations for Contract no. HY/2011/08

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.8      Real Time Noise Monitoring Stations for Contract no. HY/2011/08

Table 5.9      Air Quality Monitoring Station for Contract no. HY/2009/18 (NOT USED)

Table 5.10    Air Quality Monitoring Station for Contract no. HK/2009/01

Table 5.11    Air Quality Monitoring Station for Contract no. HK/2009/02

Table 5.12    Air Quality Monitoring Stations for Contract no. HY/2009/15

Table 5.13    Air Quality Monitoring Station for Contract no. HY/2009/19

Table 5.14    Air Quality Monitoring Station for Contract no. HK/2012/08

Table 5.15    Air Quality Monitoring Stations for Contract no. HY/2010/08

Table 5.16    Air Quality Monitoring Stations for Contract no. HY/2011/08

Table 5.17    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.18    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.20    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.21    Details of Waste Disposal for Contract no. HY/2009/19

Table 5.22    Details of Waste Disposal for Contract no. HK/2012/08

Table 5.23    Details of Waste Disposal for Contract no. HY/2010/08

Table 5.24    Details of Waste Disposal for Contract no. HY/2011/08

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/15 (NOT USED)

Table 8.2      Summary of Environmental Inspections for Contract no. HY/2009/18 (NOT USED)

Table 8.3      Summary of Environmental Inspections for Contract no. HY/2009/19

Table 8.4      Summary of Environmental Inspections for Contract no. HK/2009/01 (NOT USED)

Table 8.5      Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.6      Summary of Environmental Inspections for Contract no. HK/2012/08

Table 8.7      Summary of Environmental Inspections for Contract no. HY/2010/08 

Table 8.8      Summary of Environmental Inspections for Contract no. HY/2011/08)NOT USED)

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be    

                      commenced in Coming Reporting period

 

LIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.2    Copies of Calibration Certificates

Appendix 5.1    Monitoring Schedule for Reporting period and Coming month

Appendix 5.2    Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1    Event Action Plans

Appendix 6.2    Notification of Exceedance

Appendix 9.1    Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

 

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report – May 2018 specific for Environmental Permit no. EP-364/2009/E, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2015/01 Wan Chai Development Phase II and Central Wanchai Bypass – Sampling, Field Measurement and Testing Works (Stage 3). This report presents the environmental monitoring findings and information recorded during the period of 27 April 2018 to 26 May 2018.

 

  1. The implementation of the Environmental Monitoring and Audit Programme for the Wan Chai Development phase II and Central-Wan Chai Bypass Project has been taken over by the Lam Geotechnics Limited (LGL) under Contract HK/2015/01 Wan Chai Development Phase II and Central Wanchai Bypass – Sampling, Field Measurement and Testing Works (Stage 3) from 27 December 2015 in continuation of the previous Environmental Team employed under Contact HK/2011/07 – Wan Chai Development Phase II and Central Wanchai Bypass – Sampling, Field Measurement and Testing Works (Stage 2).

 

  1. In the reporting period, the principal work activities of individual contracts are included as follows:

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

·          Reinstatement of amenity area

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009             

·          New PMMA for the replacement of 8 nos. of damaged PMMA panels

·          Preparation for raising the vent shaft, water meters chambers and multi-part covers of P7, P8 and P9

·          Drainage work

·          Remedial works against water leakage and CCTV inside tunnel

·          Installation of breakwater

·          Backfilling behind seawall block

·          Pipe piling work for ELS of Box Culvert O Bay 13, 14

·          Installation of ELS for Box Culvert O Bay 14A and 17A

·          Backfilling works for Box Culvert O Bay 15A and 16A

·          Demolition of D-Wall for construction of Box Culvert O

·          Fabrication of precast units for Box Culvert O

·          Remedial works against water leakage inside OHVD cells

·          Temporary drainage system for stock piling at Portion 5

·          Construction of manhole no. MH4.17 for sewage works at Wan Shing Street

·          Backfilling for sewage trench at Wan Shing Street

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

·          Approach ramp structure Construction.

·          Bridge superstructure, parapet & installation of enclosure.

·          Retaining wall construction.

·          FEHD depot re-provision works.

·          FEHD metal roof construction.

·          Oil street drainage works.

·          Installation of skin parapet on TB bridge at Pier 15-17.

·          Landscape deck, column & pile cap foundation works.

·          Watson Road Watermains laying works.

·          EVA at EVB.

·          Hing Fat Street road and drainage works.

·          Demolition of TD bridge.

 

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D

·          Construction of Slip Road 1

·          Construction of drainage

·          Asphalt paving

·          Construction of roundabout

 

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B

·          Tree replanting works in VP,

·          Drainage improvement works,

·          Utility diversion works,

·          Retaining wall works

 

Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

·          Construction of Ventilation Buildings, inclusive of Administration Building, Central Ventilation Building, East Ventilation Shaft/Building, West Ventilation Building

·          Application of Thermal Barrier inside the Tunnel, asphalt pavement

·          Installation of Electricals and Mechanicals

·          Installation of Tunnel Features

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a – Footbridge for Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w – International Financial Centre East Podium and International Finance Centre West Podium and M8 – City Hall on weekly basis in the reporting period.
  2. With respect to the shift in major construction site portions at Wan Chai North, the noise monitoring station M1a – Harbour Road Sports Centre was finely adjusted from East of Harbour Road Sports Centre to West of Harbour Road Sports Centre on 21 June 2016.
  3. With respect to the demolition of Ex-Harbour Road Sports Centre, the respective noise monitoring station M1a – Harbour Road Sports Centre were finely adjusted on 16 and 25 May 2017 and thereafter to the Footbridge for Harbour Road Sports for noise monitoring.
  4. With respect to the non-CWB Project building construction at Oil Street, the real-time noise monitoring station RTN2a- Hong Kong Electric Centre was finely adjusted from Northeast Side to Northwestern side at Roof Top location on 03 March 2017.
  5. No action or limit level exceedance was recorded in the reporting month.
  6. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. No limit level exceedance was recorded in the reporting period.
  7. 24-hour real time noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. No limit level exceedance was recorded in the reporting period.
  8. 24-hour real time noise monitoring was conducted at RTN3 – Yu Lee Mo Fan Memorial School. Limit level exceedances were recorded on 27 April, 8, 9, 10 and 11 May 2018 during the monitoring period. After investigation, the exceedances recorded on 9 May 2018 were considered as Project related and the other exceedances recorded was considered as non-Project related.
  9. 24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. Limit level exceedances were recorded on 15 May 2018 during the monitoring period. After the investigation, the exceedances were considered as non-project related.

 

Air Quality Monitoring

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b – Harbour Grand Hotel Boundary Wall; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to Animals; CMA5b - Pedestrian Plaza; MA1e and MA1w – International Finance Centre eastern and western podium on every six days basis.
  2. No action or limit level exceedance was recorded in the reporting period.
  3. With respect to the proposed demolition of eastern podium of Oil Street Site Office, the respective air quality monitoring station CMA1b – Oil Street Site Office was finely adjusted from East podium of the Oil Street Site Office to the West podium of the Oil Street Site Office on 21 December 2016.
  4. With respect to the proposed demolition of the Oil Street Site Office, the respective air quality monitoring station CMA1b – Harbour Grand Hotel Boundary Wall was finely adjusted from the Oil Street Site Office to Harbor Grand Hotel Boundary Wall from 05 June 2017 onwards.
  5. One 1hr TSP action level exceedance was recorded at CMA2a – Causeway Bay Community Centre on 26 May 2018 in the reporting month. After the investigation, the exceedance was concluded as non-project related.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. Two Summons to Defendant were issued to the Contractors of Contract HY/2009/19 in the reporting month.
  2. The First Summons to Defendant was issued to the Contractors of Contract HY/2009/19 on 18 May 2018 regarding to carrying out prescribed construction work in Designated Area which was not permitted in the construction noise permit GW-RS05262-17 and contrary to Section 6(2)(b) and 6(5), Noise Control Ordinance, Cap. 400.
  3. The Second Summons to Defendant was issued to the Contractors of Contract HY/2009/19 on 18 May 2018 regarding to use powered mechanical equipment, namely a concrete lorry mixer, for the purpose of carrying out of construction work which was not permitted in the construction noise permit GW-RS05262-17 and contrary to section 6(1)(b) and 6(5), Noise Control Ordinance, Cap. 400.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/18, HY/2009/19, HY/2010/08, HK/2009/01, HK/2009/02, HK/2012/08 and HY/2011/08 in this reporting period.
  2. Construction of bored pile E3B under HY/2009/17 was confirmed completed and the respective work area under FEP-03/364/2009 was handover and inspected under HY/2009/19 from 19 Dec 2012 onwards.
  3. Construction works under HK/2010/06 was confirmed completed and the respective work area under FEP-08/364/2009/A was handover and inspected under HK/2012/08 from 22 Sep 2014 onwards.
  4. As confirmed with CWB RSS, the construction works under Contract HY/2009/15 was completed from 27 October 2017 onwards. The respective weekly site audit inspection for HY/2009/15 was therefore suspended from 27 October 2017 onwards.
  5. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.
  6. As confirmed with CWB RSS, the construction works under Contract HY/2009/18 was completed from 25 April 2018 onward. The respective weekly site audit inspection for HY/2009/18 was therefore temporary suspended from 27 April 2018 onwards.

 

Future Key Issues

  1. In the coming reporting period, the principal work activities of individual contracts are anticipated as follows:

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

·          Reinstatement of amenity area

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·          Rectification work for the replacement of 8 nos. of damaged PMMA panels

·          Drainage work

·          Remedial works against water leakage and CCTV inside tunnel

·          Partial removal of TWCR4 to -5.0mPD

·          Backfilling works behind seawall blocks and adjacent Box Culvert O

·          Construction of box culvert ‘O’

·          Temporary works for construction of box culvert ‘O’

·          Demolition of D-Wall for construction of Box Culvert O

·          Fabrication of precast units for Box Culvert O

·          Installation of tie-back

·          Remedial works against water leakage inside tunnel

·          Stockpiling and internal transfer of excavated materials from Portions 3&4

·          Monitoring and maintain temporary drainage system for stockpiling

·          Rectification works for damaged CMS cover under C1

·          Sewage works at Wan Shing Street

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

·          Bridge superstructure & installation of enclosure.

·          Retaining wall construction.

·          FEHD re-provision works.

·          Oil Street drainage works.

·          Installation of skin parapet on TB bridge at Pier 15-17.

·          Landscape deck soft landscaping works.

·          Watson Road Watermains laying works.

·          EVA at EVB.

·          Hing Fat Street road and drainage works.

·          Demolition of TD bridge

 

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D

·          Construction of Slip Road 1

·          Construction of drainage

·          Asphalt paving

·          Construction of roundabout

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009

·          Tree replanting works in VP,

·          Drainage improvement works,

·          Utility diversion works,

·          Retaining wall works

 

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

·          Construction of Ventilation Buildings, inclusive of Administration Building, Central Ventilation Building, East Ventilation Shaft/Building, West Ventilation Building

·          Application of Thermal Barrier inside the Tunnel, asphalt pavement

·          Installation of Electricals and Mechanicals

·          Installation of Tunnel Features

 

 

1            Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and Further Environmental permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/E, Further Environmental Permit (FEP) nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D during the period 27 April 2018 to 26 May 2018.

1.2          Structure of the Report

 

Section 1        Introduction – details the scope and structure of the report.

 

Section 2        Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements – summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit – summarizes the auditing of monitoring results, all  

                          exceedances environmental parameters.

 

 

 

Section 7  Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8        Environmental Site Audit – summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9        Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2      Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

·      A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

·      The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

·      Tunnel control buildings and ventilation buildings;

·      Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

·      Associated road lighting, road signing, traffic control and surveillance system; and

·      Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central – Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

(Completed)

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010 (Completed)

HK/2009/01

Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP1,DP3

13 July 2011

(Completed)

HY/2009/19

Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

10 March 2014

HY/2010/08

Central- Wanchai Bypass Tunnel – Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative for WDII

Principal Resident Engineer

Ms. Gloria Tang

2587 1778

2587 1877

Engineer’s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3912 3388

3912 3328

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Manager

Mr. Simon Liu

9304 8355

2587 1878

Environmental Officer

Mr. Terry Tsang

6683 9394

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Paul Yu

3658 3085

2827 9996

 

Environmental Officer

Mr. C.P. Ho

9191 8856

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

Project Manager

Mr. David Lau

3758 8879

2570 8013

Site Agent

Mr. William Luk

9456 9819

Deputy Site Agent

Mr. Andy Chan

3758 8879

Environmental Officer

Mr. M.H. Isa

3757 8218

Assistant Environmental Officer

Mr. James Chan

3757 8217

Construction Manager (Marine)

Mr. Wingo Wong

9300 2625

Construction Manager (Land)

Mr. Ray Ho

9608 6366

Construction Manager (Land)

Mr. Yung Kwok Wah

9834 1010

Construction Manager (Ext. Works)

Mr. Paul Wan

6629 4652

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Jimmy Chu

3973 0803

2140 6799

Construction Manager

Mr. Darren Grant

3971 1460

Environmental Supervisor

Ms. Penny Yiu

3973 1065

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. Chris Leung

3557 6393

2865 5229

Site Agent

Mr. Patrick Ho

3557 6405

2566 2192

Environmental Officer

Mr. Desmond Ho

3557 6347

China State- Build King JV

Contractor under Contract no. HK/2012/08

Project Director

Mr. C.N. Lai

9137 1811

2877 1522

Site Agent

Mr. George Cheung

9268 1918

Environmental Officer

Mr. James MA

9130 9549

Environmental Supervisor

Mr. Y. L. Ho

9856 5669

China State

Contractor under Contract no. HY/2010/08

Project Director

Chris Leung

9210 7116

2566 8061

 

 

 

Site Agent

Mr. Thomas Lui

3557 6407

Environmental Officer

Mr. Gabriel Wong

3557 6466

Leighton Joint Venture

Contractor under Contract no. HY/2011/08

Site Agent

Mr. Colman Wong

2823 1410

21406799

Environmental Officer

Ms. Penny Yiu

3973 1065

Ramboll Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.     In this reporting period, the principal work activities of individual contracts are included as follows:

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

·          Reinstatement of amenity area

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009             

·          New PMMA for the replacement of 8 nos. of damaged PMMA panels

·          Preparation for raising the vent shaft, water meters chambers and multi-part covers of P7, P8 and P9

·          Drainage work

·          Remedial works against water leakage and CCTV inside tunnel

·          Installation of breakwater

·          Backfilling behind seawall block

·          Pipe piling work for ELS of Box Culvert O Bay 13, 14

·          Installation of ELS for Box Culvert O Bay 14A and 17A

·          Backfilling works for Box Culvert O Bay 15A and 16A

·          Demolition of D-Wall for construction of Box Culvert O

·          Fabrication of precast units for Box Culvert O

·          Remedial works against water leakage inside OHVD cells

·          Temporary drainage system for stock piling at Portion 5

·          Construction of manhole no. MH4.17 for sewage works at Wan Shing Street

·          Backfilling for sewage trench at Wan Shing Street

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

·          Approach ramp structure Construction.

·          Bridge superstructure, parapet & installation of enclosure.

·          Retaining wall construction.

·          FEHD depot re-provision works.

·          FEHD metal roof construction.

·          Oil street drainage works.

·          Installation of skin parapet on TB bridge at Pier 15-17.

·          Landscape deck, column & pile cap foundation works.

·          Watson Road Watermains laying works.

·          EVA at EVB.

·          Hing Fat Street road and drainage works.

·          Demolition of TD bridge

 

 

 

 

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D

·          Construction of Slip Road 1

·          Construction of drainage

·          Asphalt paving

·          Construction of roundabout

 

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B

·          Tree replanting works in VP,

·          Drainage improvement works,

·          Utility diversion works,

·          Retaining wall works

 

Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

·          Construction of Ventilation Buildings, inclusive of Administration Building, Central Ventilation Building, East Ventilation Shaft/Building, West Ventilation Building

·          Application of Thermal Barrier inside the Tunnel, asphalt pavement

·          Installation of Electricals and Mechanicals

·          Installation of Tunnel Features

 

2.4.4.     In coming reporting period, the principal work activities of individual contracts are anticipated as follows:

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

·          Reinstatement of amenity area

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·          Rectification work for the replacement of 8 nos. of damaged PMMA panels

·          Drainage work

·          Remedial works against water leakage and CCTV inside tunnel

·          Partial removal of TWCR4 to -5.0mPD

·          Backfilling works behind seawall blocks and adjacent Box Culvert O

·          Construction of box culvert ‘O’

·          Temporary works for construction of box culvert ‘O’

·          Demolition of D-Wall for construction of Box Culvert O

·          Fabrication of precast units for Box Culvert O

·          Installation of tie-back

·          Remedial works against water leakage inside tunnel

·          Stockpiling and internal transfer of excavated materials from Portions 3&4

·          Monitoring and maintain temporary drainage system for stockpiling

·          Rectification works for damaged CMS cover under C1

·          Sewage works at Wan Shing Street

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

·          Bridge superstructure & installation of enclosure.

·          Retaining wall construction.

·          FEHD re-provision works.

·          Oil Street drainage works.

·          Installation of skin parapet on TB bridge at Pier 15-17.

·          Landscape deck soft landscaping works.

·          Watson Road Watermains laying works.

·          EVA at EVB.

·          Hing Fat Street road and drainage works.

·          Demolition of TD bridge

 

 

 

 

 

 

 

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D

·          Construction of Slip Road 1

·          Construction of drainage

·          Asphalt paving

·          Construction of roundabout

 

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009

·          Tree replanting works in VP,

·          Drainage improvement works,

·          Utility diversion works,

·          Retaining wall works

 

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

·          Construction of Ventilation Buildings, inclusive of Administration Building, Central Ventilation Building, East Ventilation Shaft/Building, West Ventilation Building

·          Application of Thermal Barrier inside the Tunnel, asphalt pavement

·          Installation of Electricals and Mechanicals

·          Installation of Tunnel Features

 

3         status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licenses

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009/E

22 Dec 2016

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Surrendered

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Surrendered

Further Environmental Permit

FEP-06/356/2009

5 March 2013

Valid

Further Environmental Permit

FEP-07/356/2009

26 July 2013

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/D

24 Nov 2015

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 June 2012

Surrendered

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

Valid

Further Environmental Permit

FEP-10/364/2009/B

26 July 2013

Valid

Further Environmental Permit

FEP-11/364/2009/E

22 Dec 2016

Valid

Further Environmental Permit

FEP-12/364/2009/D

01 Aug  2016

Valid

 

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

3.1.3.     The construction works was completed and the FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.     The construction works was completed, and the FEP-04/HY/2006 was surrendered by the Contractor on 11 February 2011.

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

3.1.5.     The construction works was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

3.1.6.     The Construction works under HY/2009/15 was confirm completed by the RSS from 27 October 2017 onwards. The weekly site audit inspection and the associated monitoring station for HY/2009/15 were temporary suspended from 27 October 2017 onwards.

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

3.1.7.     The Construction works under HY/2009/18 was confirm completed by the RSS from 25 April 2018 onwards. The weekly site audit inspection and the associated monitoring station for HY/2009/18 were temporary suspended from 27 April 2018 onwards.

 

 

 

 

 

 

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

3.1.8.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.

Table 3.2    Cumulative Summary of Valid Licences and Permits under Contract no.    HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

06 Jan 2010

N/A

Valid

Discharge License

WT00024952-2016

06 Jul 2016

31 Jul 2021

Valid

WT00024844-2016

29 Jun 2016

31 Mar 2020

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

Table 3.3    Summary of submission status under FEP-02/364/2009

EP Condition

Submission

Date of Submission

Condition 2.7 & 2.8

Works Schedule and Location Plan

18 May 2011

Condition 2.6

Environmental Management Organization Chart

18 May 2011

Condition 1.12

Commencement Date of Works

20 Jun 2011

Condition 2.9

Noise Management Plan

10 Jun 2011

Condition 2.11

Landscape Plan (Rev.5)

25 January 2018

 

 

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

3.1.9.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.

Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licenses

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for non-pilling equipment

GW-RS0296-18

10 Apr 2018

23 Apr 2018 to 22 Oct 2018

Valid

GW-RS0333-18

25 Apr 2018

27 Apr 2018 to 25 Oct 2018

Valid

GW-RS0334-18

25 Apr 2018

27 Apr 2018 to 25 Oct 2018

Valid

Water Discharge License

WT00022295-2015

12 Aug 2015

31 July 2020

Valid

WT00025276-2016

19 Sep 2016

31 July 2021

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance (Marine)

7011496

6 Oct 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

 

 

 

 

 

 

 

Table 3.5    Summary of submission status under FEP-01/364/2009

EP Condition

Submission

Date of Submission

Condition 2.7 and  2.8

Works Schedule and Location Plan

14 Jun 2011

Condition 2.6

Environmental Management Organization Chart

14 Jun 2011

Condition 1.12

Commencement Date of Works

21 Jun 2011

Condition 2.11

Landscape Plan (Revision B)

20 Nov 2012

Condition 2.9

Noise Management Plan (Revision B)

13 Jan 2012

 

 

 

 

 

 

 


Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

3.1.10.   Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table 3.7.

Table 3.6    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Permit / License / Notification / Approval

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

N/A

Valid

Notification of Works Under APCO

322293

07 Oct 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0032-18

15 Jun 2018

24 Jan 2018 to   21 Jul 2018

Valid

Discharge Licenses

WT00024255-2016

18 May 2016

31 Jan 2021

Valid

Registration as a Chemical Waste Producer

WPN: 8335-121-L1048-04

17 Dec 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance (Land)

Account No.: 7011587

11 Oct 2010

N/A

Valid

 

Table 3.7    Summary of submission status under FEP-05/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

01 March 2011

Condition 2.10

Landscape Plan (Rev. 6)

19 May 2014


Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

3.1.11.   Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.

Table 3.8    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

N/A

Valid

FEP-04/356/2009

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN: 5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

N/A

Valid

Construction Noise Permit

N/A

N/A

N/A

N/A

Water Discharge License (Discharge at TS1)

WT00024874-2016

20 Jul 2016

20 Jul 2016 to 31 Mar 2021

Valid

 

Table 3.9    Summary of submission status under FEP-06/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 Mar 2011

Amendment for Management Organization of Main Construction Companies

16 May 2011

Condition 2.7

Works Schedule

15 Mar 2011

Condition 2.8

Location Plan

15 Mar 2011

Condition 2.9

Noise Management Plan

6 May 2011

Condition 2.10

Landscape Plan (Rev.5)

25 Jan 2018

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

3.1.12.   The current status on licences and/or permits on environmental protection pertinent and submission under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table 3.11.

Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-07/364/2009/D

24 Nov 2015

N/A

Valid

Notification of Works Under APCO

326160

24 Jan 2011

N/A

Valid

Registration as a Waste Producer

7012306

10 Feb 2011

N/A

Valid

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

N/A

Valid

Application for Vessel Disposal

7012306

21 July 2011

N/A

Valid

Construction Noise Permits (CNP) for non-piling equipment

GW-RS0306-18

12 Apr 2018

14 Apr 2018 to

 11 Oct 2018

Valid

GW-RS0124-18

15 Feb 2018

17 Feb 2018 to

 14 May 2018

Expired

GW-RS0367-18

4 May 2018

14 May 2018 to 9 Aug 2018

Valid

GW-RS0249-18

27 Mar 2018

31 Mar 2018 to

 11 Jun 2018

Valid

GW-RS0297-18

12 Apr 2018

30 Apr 2018 to 11 Jun 2018

Valid

GW-RS0368-18

4 May 2018

1 Jun 2018 to 31 Aug 2018

Valid

Water Discharge License

WT00025282-2016

15 Sep 2016

30 Sep 2021

Valid

 

 Table 3.11   Summary of submission status under FEP-07/364/2009/D

EP Condition

Submission

Date of Submission

Condition 2.13

Landscape Plan (Rev.6)

29 August 2017

Condition 2.9

Noise Management Plan (Rev.4)

07 December 2017

 

 

 

 

 

 

 

 

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D

3.1.13.   The current status on licences and/or permits on environmental protection pertinent and submission under FEP-12/364/2009/D for contract no. HK/2012/08 showed in Table 3.12 and Table 3.13.

Table 3.12  Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-09/364/2009/B

5 Mar 2013

N/A

Valid

FEP-12/364/2009/D

1 Aug 2016

N/A

Valid

FEP-06/356/2009

05 Mar 2013

N/A

Valid

Notification of Works Under APCO

355439

4 Feb 2013

N/A

Valid

Registration as a Chemical Waste Producer

5213-134-C3790-01

30 Jun 2016

N/A

Valid

Billing Account under Waste Disposal Ordinance

7016883

18 Feb 2013

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0181-18

23 Feb 2018

26 Feb 2018 to   

25 Aug 2018

Valid

GW-RS1163-17

28 Dec 2017

13 Jan 2018 to

12 Jul 2018

Valid

Water Discharge License

WT00020594-2014

22 Dec 2014

31 Jan 2019

Valid

 

Table 3.13  Summary of submission status under FEP-12/364/2009/D

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan (Rev.2)

9 July 2013

Condition 2.14

Landscape Plan (Rev.4)

24 August 2015

 

 

 

 

 

C

 

 

 

 

 

 

 

 

 

Contract no. HY/2010/08 –Central – Wanchai Bypass Tunnel – Tunnel (Slip Road 8) under FEP-10/364/2009/B

3.1.14.   The current status on licences and/or permits on environmental protection pertinent and submission under FEP-10/364/2009/B for contract no. HK/2012/08 showed in Table 3.14 and Table 3.15.

Table 3.14  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-10/364/2009/B

26 Jul 2013

NA

Valid

FEP-07/356/2009

26 Jul 2013

NA

Valid

Notification of Works Under APCO

357176

2013-04-02

NA

Valid

Registration as a Chemical Waste Producer

WPN5213-147-C1169-44

2013-03-27

NA

Valid

Billing Account under Waste Disposal Ordinance

7017170

2013-03-27

NA

Valid

Water Discharge License

WT00020468-2014

03 Dec 2017

31 Jul 2018

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS1205-17

5 Jan 2018

08 Jan 2018 to 02 Jul 2018

Valid

GW-RS0374-18

8 May 2018

10 May 2018 to 9 Nov 2018

Valid

GW-RS1091-17

7 Dec 2017

9 Dec 2017 to 5 Jun 2018

Valid

GW-RS0047-18

24 Jan 2018

29 Jan 2018 to 28 Jul 2018

Valid

GW-RS0258-18

29 Mar 2018

6 Apr 2018 to 17 May 2018

Expired

GW-RS0307-18

18 Apr 2018

20 Apr 2018 to 17 Dec 2018

Valid

GW-RS0438-18

29 May 2018

31 May 2018 to 27 Jun 2018

Valid

GW-RS0447-18

30 May 2018

1 Jun 2018 to 31 Aug 2018

Valid

 

 

 

 

 

 

Table 3.15  Summary of submission status under FEP-10/364/2009/B

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan (Rev.3)

03 January 2014

Condition 2.14

Landscape Plan (Rev.2)

19 May 2014

Condition 2.16

Additional Mitigation Plan (Rev.2)

18 February 2015

 

 

 

 

 

 

 

C

 

Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

3.1.15.   The current status on licenses and/or permits on environmental protection pertinent and submission under FEP-11/364/2009/E for contract no. HY/2011/08 showed in Table 3.16 and Table 3.17.

Table 3.16  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2011/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-11/364/2009/E

22 Dec 2016

N/A

Valid

Notification of Works Under APCO

LCAC-EN-LE-00017

7 Mar 2014

N/A

Valid

Registration as a Chemical Waste Producer

5213-121-L2837-01

19 Apr 2016

N/A

Valid

5213-151-L2837-02

24 May 2016

N/A

Valid

5213-134-L2898-01

16 Nov 2015

N/A

Valid

5213-134-L2952-01

12 May 2017

N/A

Valid

Billing Account under Waste Disposal Ordinance

7019640

27 Mar 2014

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0419-18

24 May 2018

27 May 2018 to

28 Nov 2018

Valid

GW-RS0058-18

26 Jan 2018

01 Feb 2018 to

31 Jul 2018

Valid

GW-RS0063-18

26 Jan 2018

01 Feb 2018 to

31 Jul 2018

Valid

GW-RS0144-18

15 Feb 2018

24 Feb 2018 to

23 Aug 2018

Valid

GW-RS0164-18

23 Feb 2018

01 Mar 2018 to

31 Aug 2018

Valid

GW-RS0171-18

23 Feb 2018

02 Mar 2018 to

01 Aug 2018

Valid

GW-RS0183-18

28 Feb 2018

01 Apr 2018

30 Sep 2018

Valid

GW-RS0257-18

27 Mar 2018

1 May 2018 to 30 Oct 2018

Valid

GW-RS0323-18

23 Apr 2018

01 May 2018 to

30 Oct 2018

Valid

GW-RS0335-18

26 Apr 2018

06 Jan 2018 to

30 Jun 2018

Valid

GW-RS1204-17

03 Jan 2018

01 Nov 2017 to

30 Jun 2018

Valid

GW-RS0357-18

02 May 2018

04 May 2018 to

02 Oct 2018

Valid

GW-RS0369-18

04 May 2018

11 May 2018 to

31 May 2018

Valid

GW-RS1047-17

28 Nov 2017

01 Dec 2017 to

31 May 2018

Valid

GW-RS1048-17

28 Nov 2017

01 Dec 2017 to

31 May 2018

Valid

GW-RS1051-17

28 Nov 2017

01 Dec 2017 to

31 May 2018

Valid

GW-RS1203-17

03 Jan 2018

06 Jan 2018 to

30 Jun 2018

Valid

Water Discharge License

WT00022046-2015

1 Mar 2017

31 Jul 2019

Valid

WT00022753-2015

22 Jun 2017

30 Apr 2021

Valid

WT00024561-2016

30 May 2016

31 May 2021

Valid

WT00025858-2016

17 Oct 2016

31 Oct 2021

Valid

WT00026829-2017

14 Jun 2017

31 Jan 2022

Valid

WT00027343-2017

01 Mar 2017

31 Mar 2022

Valid

WT000283434-2017

09 Aug 2017

31 Aug 2022

Valid

 

 

 

 

 

 

 

 

 

 

 

Table 3.17  Summary of submission status under FEP-11/364/2009/E

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan (Rev.4)

08 Nov 2016

Condition 2.14

Landscape Plan (Rev.2)

18 Feb 2015

Condition 2.13 a)

Operational Air Quality Management Plan for West Ventilation Building (Rev.0)

25 Nov 2014

Condition 2.13 b)

Operational Air Quality Management Plan for Central Ventilation Building (Rev.0)

03 Mar 2017

Condition 2.13 c)

Operational Air Quality Management Plan for East Ventilation Building and East Vent Shaft  (Rev.0)

18 Feb 2015

Condition 2.13 d)

Operational Air Quality Management Plan for an Electrostatic Precipitator system for EVB Operation (Rev.0)

06 Apr 2017

Condition 2.13 e)

Operational Air Quality Management Plan for ventilation system of Eastern Portal of the CWB Tunnel (Rev.0)

23 Oct  2016

 

4          Monitoring Requirements

4.1          Noise Monitoring

 

Noise Monitoring Stations

4.1.1.     The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1.  Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1    Noise Monitoring Stations

Station

Description

M1a***

Footbridge for Ex-Harbour Road Sports Centre

M2b

Noon-day Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

M7e*

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8**

City Hall

Remark *: Location ID has been updated from M7 to M8 for City Hall

Remark **: M7e has become a reference station starting from 7 Aug 2012

Remarks***: The location ID of monitoring station M1a was updated as “Footbridge for Ex-Harbour Road Sports Centre” in May 2017.

 

 

Real time Noise Monitoring Stations

4.1.2.     The noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2    Real Time Noise Monitoring Stations

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitfield Depot

North Point

RTN2a

Hong Kong Electric Centre

North Point

RTN3

Po Leung Kuk Yu Lee Mo Fan Memorial School

Tin Hau

RTN4

Causeway Bay Community Centre

 

 

Noise Monitoring Parameters, Frequency and Duration

4.1.3.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.4.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

·      One set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.5.     Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 - hours basis when noise generating activities are underway:

·      One set of measurements between 0700 and 1900 hours on normal weekdays.

·      One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

·      One set of measurements between 2300 and 0700 hours on next day on everyday.

4.1.6.     If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

 

Monitoring Equipment

4.1.7.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.8.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

4.1.9.     The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements will be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.2          Air Quality Monitoring

Air Quality Monitoring Stations

4.2.1.     The air quality monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3    Air Quality Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Harbour Grand Hotel Boundary Wall**

North Point (Re-commenced on 14 November 2011)

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5b

Pedestrian Plaza***

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (Western End of Podium)

Central

Remarks*: As per the ENPC meeting in March 2011, the monitoring stations CMA3a Future CWB site office at Wanchai Waterfront Promenade was renamed as remark.

 

Remarks**: The location ID of monitoring station CMA1b was updated as Oil Street Site Office in April 2013. The location ID of monitoring station CMA1b was updated as Harbour Grand Hotel Boundary Wall with respect to the fine adjustment of monitoring station from the Oil Street Site Office to Harbour Grand Hotel Boundary Wall from 05 June 2017 onwards due to demolition of Oil Street Site Office.

 

Remarks***: The station ID and monitoring location was updated in December 2014 with respect to monitoring station relocation.

 

Air QUALITY Monitoring Parameters, Frequency and Duration

4.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

·      0.6 – 1.7 m3 per minute adjustable flow range;

·      Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

·      Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·      Capable of providing a minimum exposed area of 406 cm2;

·      Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·      Equipped with a shelter to protect the filter and sampler;

·      Incorporated with an electronic mass flow rate controller or other equivalent devices;

·      Equipped with a flow recorder for continuous monitoring;

·      Provided with a peaked roof inlet;

·      Incorporated with a manometer;

·      Able to hold and seal the filter paper to the sampler housing at horizontal position;

·      Easily changeable filter; and

·      Capable of operating continuously for a 24-hour period.

 

4.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.     Filter paper of size 8” x 10” shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24 hours and be pre-weighed before use for the sampling.

4.2.9.     After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.10.   All the collected samples shall be kept in a good condition for 6 months before disposal.

4.2.11.   Current calibration certificates of equipments are presented in Appendix 4.2.

5        Monitoring Results

5.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designated project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.     In the reporting period, the concurrent contracts are as follows:

Ÿ  Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ  Contract no. HY/2010/08 – Central- Wanchai Bypass Tunnel (Slip Road 8 Section)

Ÿ  Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre

Ÿ  Contract no. HK/2009/02 - Wan Chai Development Phase II – Central - Wan Chai Bypass at Wan Chai East

Ÿ  Contract no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai West

Ÿ  Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB)– Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

5.0.3.     The environment monitoring schedules for reporting period and coming month are presented in Appendix 5.1.

 

 

 

 

5.1          Noise Monitoring Results

5.1.1       Monitoring for report of review baseline noise level was performed from 11 April 2011 to 8 June 2011.  Then the report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012.  The new baseline is used for the noise calculation starting from January 2012.

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.1.2       The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.2 below.

Table 5.2    Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Station

Description

M1a

Footbridge for Ex-Harbour Road Sports Centre

 

5.1.3       No action or limit level exceedance was recorded in this reporting period.

5.1.4       Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

 

5.1.5       Noise monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.4 below.

 

Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/19

Station

Description

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

5.1.6       No action or limit level exceedance was recorded in this reporting period.

5.1.7       Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.  Details of the Notification of Exceedance can be referred in Appendix 6.2.

 

Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-12/364/2009/D

5.1.8       The commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02 September 2013. The proposed divisions of noise monitoring stations are summarized in Table 5.5 below.

Table 5.5    Noise Monitoring Stations for Contract no. HY/2010/08

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

5.1.9       No action or limit level exceedance was recorded in this reporting period.

5.1.10    Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. 

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

5.1.11    Noise monitoring for the Central Interchange works under contract no. HY/2011/08 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2011/08 are summarized in Table 5.6 below:

 

Table 5.6    Noise Monitoring Stations for Contract no. HY/2011/08

Station

Description

M4b

Victoria Centre

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8

City Hall

* Remark: M7e has become a reference station starting from 7 Aug 2012

5.1.12    No action or limit level exceedance was recorded in this reporting period.

5.1.13    Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

5.2            Real Time Noise Monitoring Results

5.2.1.     Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013. The baseline noise level of RTN4- Causeway Bay Community Centre has adopted the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.

5.2.2.     Po Leung Kuk Yu Lee Mo Fan Memorial School granted permission for set up on 4 Sep 2012 and real time noise monitoring station RTN3 set up was performed on 14 Sep 2012. Real time noise baseline capturing was conducted during time period without construction work from 21 Sep 2012 to 04 Oct 2012. Real time noise monitoring at RTN3 – Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.

5.2.3.     Real-time noise monitoring station RTN2 previously located at oil Street Community Liaison Centre was relocated to Hong Kong Electric Centre on 5 Oct 2012, which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted at Hong Kong Electric Centre from 4 December 2009 to 17 December 2009.

5.2.4.     Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.

5.2.5.     With respect to the non-CWB Project building construction at Oil Street, the real-time noise monitoring station RTN2a- Hong Kong Electric Centre was finely adjusted from Northeast Side to Northwestern side at Roof Top location on 03 March 2017.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

5.2.6.     The proposed division of noise monitoring stations are summarized in Table 5.7 below. Real time noise monitoring for major construction works under contract no. HY/2009/19 was commenced on 24 April 2011.

Table 5.7    Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitfield Depot

RTN2a

North Point

Hong Kong Electric Centre

RTN3

North Point

Po Leung Kuk Yu Lee Mo Fan Memorial School

RTN4

Tin Hau

Causeway Bay Community Centre

* Real time noise monitoring results and graphical presentation during restrict hours and night time period are for information only and noise during CNP period shall be controlled under NCO.

 

5.2.7.     No limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot in the reporting period.

5.2.8.     No limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

5.2.9.     Limit level exceedances were recorded at RTN3 - Yu Lee Mo Fan Memorial School was recorded on 27 April 2018, 8, 9, 10 and 11 May 2018.

After checking with Contractor of HY/2009/19, no construction works was conducted on 27 April 2018 during the monitoring period. In view of the above, the exceedance was considered as non-project related and potentially contributed by nearby IEC traffic.

After checking with Contractor of HY/2009/19, saw cutting works was conducted on 8 May 2018 during the monitoring period. Contractor mitigation measure including deployment of temporary noise barriers were generally in order while heavy raining and thunderstorm were recorded in the monitoring period. As such, the exceedance was considered as non-project related and potentially contributed by adverse weather.

After checking with Contractor of HY/2009/19, saw cutting works was conducted on 9 May 2018 during the monitoring period meanwhile contractor mitigation measure including deployment of temporary noise barriers were observed not completely shielded the saw cutting machine. As such, the exceedances at the relevant period were considered as project related. Remedial action including deployment of temporary to completely shield the saw cutting machine was implement by the Contractor and no further project related exceedance was recorded.

After checking with Contractor of HY/2009/19, saw cutting works was conducted on 10 May 2018 during the monitoring period. Contractor mitigation measure including deployment of temporary noise barriers were generally in order while heavy raining was recorded in the monitoring period. As such, the exceedance was considered as non-project related and potentially contributed by adverse weather.

After checking with Contractor of HY/2009/19, saw cutting works was conducted on 11 May 2018 during the monitoring period. Contractor mitigation measure including deployment of temporary noise barriers were generally in order. As such, the exceedance was considered as non-project related and potentially contributed by nearby IEC traffic.

5.2.10.   Limit level exceedance was recorded on 15 May 2018 at RTN4- Causeway Bay Community Centre was recorded in the reporting period.

After checking with Contractor of HY/2009/19, no construction works was conducted on 15 May 2018 during the monitoring period. Non-CWB chilling system maintenance works was observed at the area opposite to the monitoring station. In view of the above, the exceedances were considered as non-Project and potentially contributed by nearby non-CWB chilling system maintenance works.

5.2.11.   Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4.


Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

5.2.12.   The proposed division of noise monitoring stations are summarized in Table 5.8 below. Real time noise monitoring for major construction works under contract no. HY/2011/08 was commenced on 19 March 2015.

     Table 5.8 Real Time Noise Monitoring Stations for Contract no. HY/2011/08

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitfield Depot

RTN2a

North Point

Hong Kong Electric Centre

RTN4

Tin Hau

Causeway Bay Community Centre

*Real time noise monitoring results and graphical presentation during restrict hours and night time period are for information only and noise during CNP period shall be controlled under NCO.

5.2.13.   No limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot in the reporting period.

5.2.14.   No limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

5.2.15.   Limit level exceedance was recorded on 15 May 2018 at RTN4- Causeway Bay Community Centre was recorded in the reporting period.

After checking with Contractor of HY/2011/08, plastering work, tile fixing work, green roof installation works and equipment and system testing works was conducted at EVB on 15 May 2018 during the monitoring period while Non-CWB chilling system maintenance works was observed at the area opposite to the monitoring station and considered as major noise contribution.  In view of the above, the exceedances were considered as non-Project and potentially contributed by nearby non-CWB chilling system maintenance works.

 

5.3       Air Quality Monitoring Results

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

5.3.1       The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized in Table 5.10 below.

Table 5.10 Air Quality Monitoring Station for Contract no. HK/2009/01

Station

Description

CMA5b

Pedestrian Plaza

5.3.2       No action or limit level exceedance was recorded in the reporting period.

5.3.3       Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.3.4       The commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of air quality monitoring stations are summarized in Table 5.11 below.

Table 5.11 Air Quality Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA3a

CWB site office at  Wanchai Waterfront Promenade

CMA4a

Society for the Prevention of Cruelty to Animals

5.3.5       No action or limit level exceedance was recorded in the reporting period.

5.3.6       Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

 

 

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

5.3.7       The proposed division of air quality monitoring stations are summarized in Table 5.13 below. Air quality monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.

Table 5.13 Air Quality Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Harbour Grand Hotel Boundary Wall

CMA2a

Causeway Bay Community Centre

5.3.8       One 1hr TSP action level exceedance was recorded at CMA2a – Causeway Bay Community Centre on 26 May 2018 in the reporting period.

No construction works was conducted under HY/2009/19 on the monitoring date and no particular observation regarding to air quality impact was observed during sampling. Meanwhile, non WDII-CWB Project construction works was observed opposite to the monitoring station. In view of the above, the exceedance was considered to be not related to the Project works under Contract HY/2009/19 and potentially contributed by non-WDII-CWB project construction works was observed opposite to the monitoring station. Nevertheless, the Contractor of HY/2009/19 was reminded to provide regularly dust suppression measures if any potential dust generating operation around the concerned location would be required to avoid any potential cumulative air quality impact.

5.3.9       Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3.

 

Contract no. HK/2012/08- Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai West

5.3.10    The commencement of construction works for Contract no. HK/2012/08 under FEP-09/364/2009/B was on May 2014. Air quality monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized in Table 5.14 below.

Table 5.14 Air Quality Monitoring Station for Contract no. HK/2012/08

Station

Description

CMA5b

Pedestrian Plaza

5.3.11    No action or limit level exceedance was recorded in the reporting period.

5.3.12    Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-12/364/2009/D

5.3.13    The commencement of construction works for Contract no. HY/2010/08 under FEP-12/364/2009/D was on July 2014. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized in Table 5.15 below.

Table 5.15 Air Quality Monitoring Station for Contract no. HY/2010/08

Station

Description

CMA3a

CWB PRE Site Office

5.3.14    No action or limit level exceedance was recorded in the reporting period.

5.3.15    Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

5.3.16    Air quality monitoring for the Central Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011. The proposed division of air quality monitoring stations are summarized in Table 5.16 below.

Table 5.16   Air Quality Monitoring Stations for Contract no. HY/2011/08

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

CMA1b

Harbour Grand Hotel Boundary Wall

CMA2a

Causeway Bay Community Centre

CMA5b

Pedestrian Plaza

5.3.17    One 1hr TSP action level exceedance was recorded at CMA2a – Causeway Bay Community Centre on 26 May 2018 in the reporting period.

Plastering work, tile fixing work, Green roof installation works and Equipment and System testing works was conducted under HY/2011/08 at EVB on the monitoring date and no particular observation regarding to air quality impact was observed during sampling. Meanwhile, non WDII-CWB Project construction works was observed opposite to the monitoring station. In view of the above, the exceedance was considered to be not related to the Project works under Contract HY/2011/08 and potentially contributed by non-WDII-CWB project construction works was observed opposite to the monitoring station. Nevertheless, the Contractor of HY/2011/08 was reminded to provide regularly dust suppression measures if any potential dust generating operation around the concerned location would be required to avoid any potential cumulative air quality impact.

5.3.18    Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

5.4       Waste Monitoring Results

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

5.4.1.     Inert C&D wastes and non-inert C&D wastes were disposed in this reporting period. Details of the waste flow table are summarized in Table 5.17.

Table 5.17  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

Nil

108087.815

TKO137, TM38

Inert C&D materials recycled, m3

Nil

98512.03

N/A

Non-inert C&D materials disposed, m3

Nil

5346.08

SENT Landfill

Non-inert C&D materials recycled, kg

Nil

1285746

N/A

Chemical waste disposed, kg

Nil

10400

N/A

Marine Sediment

(Type 1 – Open Sea Disposal) , m3

Nil

11527

South of Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

Nil

16261

East of Cha Chau

South Brothers

           

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.4.2.     Inert C&D & non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 5.18.

Table 5.18   Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

276.7

523007.21

TKO137, TM 38

Inert C&D materials recycled, m3

Nil

46520

N/A

Non-inert C&D materials disposed, m3

13.6

5615.32

SENT Landfill

Non-inert C&D materials recycled, m3

Nil

N/A

N/A

Chemical waste disposed, kg

Nil

17718

N/A

Marine Sediment (Type 1 – Open Sea Disposal) , m3

Nil

65663

South Cheung Chau

             

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under

FEP-05/364/2009/A

 

5.4.3.     Inert C&D and non-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 5.19.

Table 5.19  Details of Waste Disposal for Contract no. HY/2009/18

Waste Type

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

Nil

1415580.18

T.K.O. 137, TM 38

Inert C&D materials recycled, m3

Nil

58787.05

N/A

Non-inert C&D materials disposed, m3

Nil

4572.26

SENT Landfill

Non-inert C&D materials recycled, ton

Nil

878.37

N/A

Chemical waste disposed, kg

Nil

6772

N/A

 

 

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

5.4.4.     Inert & Non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 5.20.

Table 5.20   Details of Waste Disposal for Contract no. HY/2009/15

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

Nil

Nil

625200.92

245453.3

Tuen Mun Area 38

TKO137 FB

Inert C&D materials recycled, m3

Nil

358660.77

HY/2009/11

ex-PCWA

TS4 /TS2

WDII

Lun Ku Tan

WENT

HY/2010/08

Non-inert C&D materials disposed, m3

Nil

Nil

4675.67

1.58

SENT Landfill

WENT Landfill

Non-inert C&D materials recycled, m3

Nil

5496446.2

Xun Xiang Metalware Skylight Recycle (paper)

Chemical waste disposed, kg

Nil

22755

 

Dunwell Group

 

Marine Sediment (Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined Marine Disposal), m3

Nil

5684

South of the Brothers

           

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

5.4.5.     Inert and Non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 5.21.

Table 5.21   Details of Waste Disposal for Contract no. HY/2009/19

Waste Type

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, ton

2594.53

786912.47

TM38

Inert C&D materials recycled, ton

Nil

82349.7

N/A

Non-inert C&D materials disposed, ton

229.64

7523.02

SENT Landfill

Non-inert C&D materials recycled, ton

Nil

565.63

N/A

Chemical waste disposed, kg

Nil

11.26

N/A

Marine Sediment (Tunnel) (Type-1 Open Sea Disposal), m3

Nil

20737.96

South of Cheung Chau

Marine Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 – Confined Marine Disposal), m3

Nil

30751

East of Sha Chau

Marine Sediment (Approach Ramp) (Type 2 – Confined Marine Disposal), m3

Nil

6491

East of Sha Chau

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D

5.4.6.     No inert and Non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 5.22.

Table 5.22  Details of Waste Disposal for Contract no. HK/2012/08

Waste Type

Quantity this month*

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

105

63

184583

117263

TKO 137

TM38

Inert C&D materials recycled, m3

Nil

Nil

N/A

Non-inert C&D materials disposed, m3

100

9072

SENT

Non-inert C&D materials recycled, m3

Nil

Nil

N/A

Chemical waste disposed, kg

Nil

Nil

N/A

Marine sediment (Type 1) disposal, m3

Nil

3145

South of Cheung Chau / East of Sha Chau / South of The Brothers

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2010/08 Central – Wan Chai Bypass (CWB) – Tunnel (Slip Road 8) under FEP-10/364/2009/B

5.4.7.     No inert and Non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 5.23.

Waste Type*

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

1787.461

Nil

Nil

Nil

594205.931

262656.6

82911.8

72704.53

TM 38 / CW / TKO137SF

WENT

SENT

TKO area 137

Inert C&D materials recycled, m3

Nil

Nil

N/A

Non-inert C&D materials disposed, m3

43.489

5980.249

SENT / WENT

Non-inert C&D materials recycled, m3

Nil

Nil

N/A

Chemical waste disposed, kg

Nil

1431

N/A

Type 1 – Open Sea Disposal,  m3

Nil

16368.4

East Sha Chau/ South Brothers Island

Type 2 – Confined Marine disposal,  m3

Nil

549.2

East Sha Chau

Table 5.23 Details of Waste Disposal for Contract no. HY/2010/08

 

 

 

 

 

 

 

 

 

 

 

 

    

 

 

 

 

 

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings,    Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

5.4.8.     No inert and Non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 5.24.

Table 5.24 Details of Waste Disposal for Contract no. HY/2011/08

Waste Type*

Quantity this month

Cumulative-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

345.406

5163.746

CWPF & TKO137

Inert C&D materials recycled, m3

Nil

Nil

N/A

Non-inert C&D materials disposed, m3

325.456

7039.494

SENT

Non-inert C&D materials recycled, ton

15.16

179.92

N/A

Chemical waste disposed, kg

Nil

3800

N/A

Remark: The quantity of non-inert C&D material disposed in March 2018 was clarified as 459.60 ton and the cumulative non-inert C&D material disposed in April 2018 was clarified as 6714.038 ton.

6        Compliance Audit

6.0.1.     The Event Action Plan for construction noise, air qualities are presented in Appendix 6.1.

6.1          Noise Monitoring

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention Exhibition Centre – Tunnel Works under FEP-02/364/2009

6.1.1.     No action or limit level exceedance was recorded in the reporting period.

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.1.2.     No action or limit level exceedance was recorded in the reporting period.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

6.1.3.     No action or limit level exceedance was recorded in the reporting period.

Contract no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B

 

6.1.4.     No action or limit level exceedance was recorded in the reporting period.

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

6.1.5.     No action or limit level exceedance was recorded in the reporting period.

Real Time Noise Monitoring

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

6.1.6.     No limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot in the reporting period.

6.1.7.     No limit level exceedances were recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

6.1.8.     Limit level exceedances were recorded at RTN3 - Yu Lee Mo Fan Memorial School was recorded on 27 April 2018, 8, 9, 10 and 11 May 2018.

After checking with Contractor of HY/2009/19, no construction works was conducted on 27 April 2018 during the monitoring period. In view of the above, the exceedance was considered as non-project related and potentially contributed by nearby IEC traffic.

After checking with Contractor of HY/2009/19, saw cutting works was conducted on 8 May 2018 during the monitoring period. Contractor mitigation measure including deployment of temporary noise barriers were generally in order while heavy raining and thunderstorm were recorded in the monitoring period. As such, the exceedance was considered as non-project related and potentially contributed by adverse weather.

After checking with Contractor of HY/2009/19, saw cutting works was conducted on 9 May 2018 during the monitoring period meanwhile contractor mitigation measure including deployment of temporary noise barriers were observed not completely shielded the saw cutting machine. As such, the exceedances at the relevant period were considered as project related. Remedial action including deployment of temporary to completely shield the saw cutting machine was implement by the Contractor and no further project related exceedance was recorded.

After checking with Contractor of HY/2009/19, saw cutting works was conducted on 10 May 2018 during the monitoring period. Contractor mitigation measure including deployment of temporary noise barriers were generally in order while heavy raining was recorded in the monitoring period. As such, the exceedance was considered as non-project related and potentially contributed by adverse weather.

After checking with Contractor of HY/2009/19, saw cutting works was conducted on 11 May 2018 during the monitoring period. Contractor mitigation measure including deployment of temporary noise barriers were generally in order. As such, the exceedance was considered as non-project related and potentially contributed by nearby IEC traffic.

6.1.9.     Limit level exceedance was recorded on 15 May 2018 at RTN4- Causeway Bay Community Centre was recorded in the reporting period.

After checking with Contractor of HY/2009/19, no construction works was conducted on 15 May 2018 during the monitoring period. Non-CWB chilling system maintenance works was observed at the area opposite to the monitoring station. In view of the above, the exceedances were considered as non-Project and potentially contributed by nearby non-CWB chilling system maintenance works.

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

6.1.10.   No limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot in the reporting period.

6.1.11.   No limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

6.1.12.   Limit level exceedance was recorded on 15 May 2018 at RTN4- Causeway Bay Community Centre was recorded in the reporting period.

After checking with Contractor of HY/2011/08, plastering work, tile fixing work, green roof installation works and equipment and system testing works was conducted at EVB on 15 May 2018 during the monitoring period while Non-CWB chilling system maintenance works was observed at the area opposite to the monitoring station and considered as major noise contribution.  In view of the above, the exceedances were considered as non-Project and potentially contributed by nearby non-CWB chilling system maintenance works.


6.2          Air Quality Monitoring

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

6.2.1.     No action or limit level exceedance was recorded in the reporting period.

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.2.2.     No action or limit level exceedance was recorded in the reporting period.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

6.2.3.     One 1hr TSP action level exceedance was recorded at CMA2a – Causeway Bay Community Centre on 26 May 2018 in the reporting period.

After the investigation, No construction works was conducted under HY/2009/19 on the monitoring date and no particular observation regarding to air quality impact was observed during sampling. Meanwhile, non WDII-CWB Project construction works was observed opposite to the monitoring station. In view of the above, the exceedance was considered to be not related to the Project works under Contract HY/2009/19 and potentially contributed by non-WDII-CWB project construction works was observed opposite to the monitoring station. Nevertheless, the Contractor of HY/2009/19 was reminded to provide regularly dust suppression measures if any potential dust generating operation around the concerned location would be required to avoid any potential cumulative air quality impact.

Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D

6.2.4.     No action or limit level exceedance was recorded in the reporting period.

Contract no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B

6.2.5.     No action or limit level exceedance was recorded in the reporting period.

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

6.2.6.     One 1hr TSP action level exceedance was recorded at CMA2a – Causeway Bay Community Centre on 26 May 2018 in the reporting period.

After the investigation, Plastering work, tile fixing work, Green roof installation works and Equipment and System testing works was conducted under HY/2011/08 at EVB on the monitoring date and no particular observation regarding to air quality impact was observed during sampling. Meanwhile, non WDII-CWB Project construction works was observed opposite to the monitoring station. In view of the above, the exceedance was considered to be not related to the Project works under Contract HY/2011/08 and potentially contributed by non-WDII-CWB project construction works was observed opposite to the monitoring station. Nevertheless, the Contractor of HY/2011/08 was reminded to provide regularly dust suppression measures if any potential dust generating operation around the concerned location would be required to avoid any potential cumulative air quality impact.

6.3          Review of the Reasons for and the Implications of Non-compliance

6.3.1       There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.3.2       Project related noise limit level exceedances under Contract HY/2009/19 was recorded on 9 May 2018 during the monitoring period meanwhile contractor mitigation measure including deployment of temporary noise barriers were observed not completely shielded the saw cutting machine and was considered as major contribution to the measured noise level.

6.4          Summary of action taken in the event of and follow-up on non-compliance

6.4.1       Remedial action including deployment of temporary to completely shield the saw cutting machine was implement by the Contract HY/2009/19 and no further project related exceedance was recorded.

 

 

7        Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-364/2009/E, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.     According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011.  As such, it is considered that there were no cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) undertaken by contractor HK12/02 in the reporting period.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area include roadworks, drainage and asphalt paving were performed in May 2018 reporting period. As no project related exceedance were recorded during the reporting period, cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was considered as insignificant.

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activities under Wan Chai Development Phase II were road and drains construction and removal of temporary reclamation at Wan Chai. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were drainage works and ventilation building construction at Central; reinstatement works along Causeway Bay Typhoon Shelter, road works and landscape works at Victoria Park; bridge construction, approach ramp construction, landscape deck construction and ventilation building construction at North Point area in the reporting period. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects were observed undertaken at Wan Chai North and North Point area.

7.0.5.     As relevant site mitigation measures for air quality and construction noise were implemented, no significant air quality impact and noise impact from construction activities was concluded in the reporting period. Besides, no project related exceedance was recorded during the air quality and noise environmental monitoring events in the reporting period. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was insignificant.

 8              Enviromental site audit

8.0.1.           During this reporting period, weekly environmental site audits were conducted for Contracts HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02, HY/2010/08 and HY/2011/08. No non-conformance was identified during the site audits. The Contractors rectified major observations and recommendations made during the audit sessions.

8.0.2.           Site inspections for Contract no. HY/2009/19 were carried out during this reporting period. No observation was found in the reporting period.

8.0.3.           Site inspections for Contract no. HK/2009/01 was carried out during this reporting period.    No observation was found in the reporting period.

8.0.4.           Site inspections for Contract no. HK/2009/02 were carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.5.

          Table 8.5     Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Completion date

180503_01

3 May 2018

Tarpaulin sheet shall be deployed properly during material transport to avoid material drop off (Portion 3&4)

Material transport was observed suspended.

Completion as observed on 9 May 2018

180515_01

15 May 2018

Tarpaulin sheet shall be deployed during material transfer to avoid drop-off (Portion 3&4)

No further material transfer was observed.

Completion as observed on 24 May 2018

180515_02

15 May 2018

Contractor shall enhance the wheel washing system and provide cleaning to public road if necessary (Hung Hing Road)

Wheel washing system was enhanced and no further muddy trail was observed at site exit.

Completion as observed on 24 May 2018

180515_03

15 May 2018

Covering shall be provided to cement bags stored on-site (Portion 3&4)

Cement bags stored on-site was covered.

Completion as observed on 24 May 2018

 

8.0.5.           Site inspection for Contract no. HK/2012/08 were carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.6.

           Table 8.6     Summary of Environmental Inspections for Contract no. HK/2012/08

Item

Date

Observations

Action taken by Contractor

Completion date

180430_01

30 Apr 2018

Sufficient dust mitigation shall be provided to dusty surface to avoid dust emission. (Zone C)

Watering was provided to dusty surface

Completion as observed on 8 May 2018

180514_01

14 May 2018

Environmental permit shall be display at site entrance for inspection (Lung King Street)

Environmental Permit was displayed at the site entrance

Completion as observed on 21 May 2018

180514_02

14 May 2018

Silt / sand deposit at the site entrance shall be cleaned regularly.

No further deposition of sand / silt at the site entrance was observed

Completion as observed on 21 May 2018

180514_03

14 May 2018

Contractor shall critically review the dosage of wastewater treatment unit and repair the damaged put of treatment unit prior to further discharge (Lung King Street)

Wastewater treatment unit was observed operated in normal condition.

Completion as observed on 21 May 2018

180521_01

21 May 2018

Watering shall be provided to breaking works (Zone C)

Breaking works was observed suspended

Completion as observed on 29 May 2018

 

8.0.6.           Site inspections for Contract no. HY/2010/08 were carried out during this reporting period. No observation was found in the reporting period.

          Table 8.7     Summary of Environmental Inspections for Contract no. HY/2010/08

Item

Date

Observations

Action taken by Contractor

Completion date

180511_1

11-May-18

Contractor shall clear the mud sitting around the discharge location to avoid surface runoff (Victoria Park)

Mud sitting around the discharge location was clear

Completion as observed on 16 May 2018

180516_1

16-May-18

Silt screen arrangement shall be resumed according to the silt screen deployment plan after the pumping test (TS3)

Cooling water intake diversion was conducted by contractor and silt screen and relevant protective measure was installed accordingly

Completion as observed on 23 May 2018

 

8.0.7.           Site inspections for Contract no. HY/2011/08 were carried out during this reporting period. No observation was found in the reporting period.

 

9        Complaints, Notification of Summons and Prosecution

9.0.1.     Two Summons to Defendant were issued to the Contractors of Contract HY/2009/19 in the reporting month.

The First Summons to Defendant was issued to the Contractors of Contract HY/2009/19 on 18 May 2018 regarding to carrying out prescribed construction work in Designated Area which was not permitted in the construction noise permit GW-RS05262-17 and contrary to Section 6(2)(b) and 6(5), Noise Control Ordinance, Cap. 400.

The Second Summons to Defendant was issued to the Contractors of Contract HY/2009/19 on 18 May 2018 regarding to use powered mechanical equipment, namely a concrete lorry mixer, for the purpose of carrying out of construction work which was not permitted in the construction noise permit GW-RS05262-17 and contrary to section 6(1)(b) and 6(5), Noise Control Ordinance, Cap. 400.

9.0.2.     The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.3.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

May 2018

0

September 2010 – April 2018

94

Total

94

 

Table 9.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

1

0

1

Noise

1

0

1

Water

0

0

0

Waste

0

0

0

Total

2

                         0

2

10         Conclusion

10.0.1.   The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.   The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1. The construction programmes of individual contracts are provided in Appendix 10.1.

Table 10.1  Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting period

Contract No.

Key Construction Works

Recommended Mitigation Measures

HY/2009/19

·         Bridge superstructure & installation of enclosure.

·         Retaining wall construction.

·         FEHD re-provision works.

·         Oil Street drainage works.

·         Installation of skin parapet on TB bridge at Pier 15-17.

·         Landscape deck soft landscaping works.

·         Watson Road Watermains laying works.

·         EVA at EVB.

·         Hing Fat Street road and drainage works.

·         Demolition of TD bridge

·         Noise level shall be controlled by reducing the breaking operation rate.

·         Noise barrier shall be implemented

·         Dust control during dust generating works

·         Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system or the sea.

HK/2009/01

 

·         Reinstatement of amenity area

 

·         Dust control during dust generating works

HK/2009/02

·         Rectification work for the replacement of 8 nos. of damaged PMMA panels

·         Drainage work

·         Remedial works against water leakage and CCTV inside tunnel

·         Partial removal of TWCR4 to -5.0mPD

·         Backfilling works behind seawall blocks and adjacent Box Culvert O

·         Construction of box culvert ‘O’

·         Temporary works for construction of box culvert ‘O’

·         Demolition of D-Wall for construction of Box Culvert O

·         Fabrication of precast units for Box Culvert O

·         Installation of tie-back

·         Remedial works against water leakage inside tunnel

·         Stockpiling and internal transfer of excavated materials from Portions 3&4

·         Monitoring and maintain temporary drainage system for stockpiling

·         Rectification works for damaged CMS cover under C1

·         Sewage works at Wan Shing Street

·         Dust control during dust generating works

·         Proper maintenance boundary surface runoff protection and water treatment facilities to avoid potential runoff related impact.

·         Provision of protection measures to ensure no runoff out of site area or direct discharge into public drainage system.

HK/2012/08

·         Construction of Slip Road 1

·         Construction of drainage

·         Asphalt paving

·         Construction of roundabout

·         Dust control during dust generating works

·         Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system.

HY/2010/08

·         Tree replanting works in VP,

·         Drainage improvement works,

·         Utility diversion works,

·         Retaining wall works

 

·         Dust control during dust generating works and stockpile stored on site.

·         Appropriate measures should be taken to ensure adequate protections are provided for trees being transplanted and retained on site.

·         Provision of protection to ensure no runoff out of site area or direct discharge into public drainage system.

HY/2011/08

·         Construction of Ventilation Buildings, inclusive of Administration Building, Central Ventilation Building, East Ventilation Shaft/Building, West Ventilation Building

·         Application of Thermal Barrier inside the Tunnel, asphalt pavement

·         Installation of Electricals and Mechanicals

·         Installation of Tunnel Features

·         Dust control during dust generating works

 

 

10.0.3.   The construction works of Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by the Contractor on 11 February 2011.

10.0.4.   The construction works of Contract no. HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was completed, and the FEP was surrendered by the Contractor and found in order by EPD on 25 April 2013.

10.0.5.   The construction works of Contract HK/2010/06 was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.

10.0.6.   The Construction works under HY/2009/15 was confirm completed by the RSS from 27 October 2017 onwards.

10.0.7.   The Construction works under HY/2009/18 was confirm completed by the RSS from 25 April 2018 onwards.